Table of Contents

BEC PLANS FOR ABACO

During a meeting held at Abaco Central Secondary School on 20th August, Bahamas Electricity Corporation General Manager Freeman Duncanson outlined the Corporation's immediate plans for Abaco.

Abaco was the fastest growing community in The Bahamas in terms of power needs, Mr Duncanson noted. BEC was determined to keep up with Abaco's needs. By the end of this year BEC would be bringing electricity to Treasure Cay and Man O' War Cay. An additional 5 megawatts of power will be added to the grid and BEC would be providing electricity to every settlement on Abaco and its cays from Crown Haven to Crossing Rocks from its Marsh Harbour power station.

Sandy Point would, for the time being, remain with its present BEC station.

Table of Contents

Copyright © 1997
Out Island Internet
Abacom Ltd.
Marsh Harbour
Abaco, Bahamas
August 24, 1997
All rights reserved.
webmaster@oii.net
>